I have begun using the adavanced roadmaps functionality and I am unable to :
1. Set sprint start and finish dates
2. Assign tasks to sprints
Why is there no sprint option in the dropdown?
Hi @brad walls,
Have a look at the data sources of your plan. My guess is you are importing data from a project or a filter, while sprints are associated with a scrum board.
If I'm right, rather use your scrum board as a data source instead to pull in your sprints.
You'll be able to add issues to a sprint then, but creating and scheduling your sprints is done in the scrum board, not in your roadmap.