I have begun using the adavanced roadmaps functionality and I am unable to :
1. Set sprint start and finish dates
2. Assign tasks to sprints
Why is there no sprint option in the dropdown?
Community moderators have prevented the ability to post new answers.
Hi @brad walls,
Have a look at the data sources of your plan. My guess is you are importing data from a project or a filter, while sprints are associated with a scrum board.
If I'm right, rather use your scrum board as a data source instead to pull in your sprints.
You'll be able to add issues to a sprint then, but creating and scheduling your sprints is done in the scrum board, not in your roadmap.