Time remaining calculation is incorrect

I have a task...

  • Original Estimate:  3d 1h
  • Time Spent:  3d 2h
  • Time Remaining:  1d 6h

It should show 0h or -1h remaining ... help...

 

image2014-11-7 5:56:35.png

2 answers

0 vote

Ah, no.   Estimated = 3d 1h.  That's not the original estimate, it's the current.  1d 6h left to go, and logged 3d 2h.  Have a look at the history, you should see the original esttmate is 4d 7h.

0 vote

The time remaining is not always calculated based on Estimated - Logged. You have an option to update the time remaining when a time is logged (i.e. because the original estimate may not always be accurate).

Check the history tab to see if "Time remaining" was manually altered or not.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

13,137 views 15 13
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you