Time remaining calculation is incorrect

I have a task...

  • Original Estimate:  3d 1h
  • Time Spent:  3d 2h
  • Time Remaining:  1d 6h

It should show 0h or -1h remaining ... help...

 

image2014-11-7 5:56:35.png

2 answers

0 votes

Ah, no.   Estimated = 3d 1h.  That's not the original estimate, it's the current.  1d 6h left to go, and logged 3d 2h.  Have a look at the history, you should see the original esttmate is 4d 7h.

0 votes

The time remaining is not always calculated based on Estimated - Logged. You have an option to update the time remaining when a time is logged (i.e. because the original estimate may not always be accurate).

Check the history tab to see if "Time remaining" was manually altered or not.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

573 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you