Sprint won't close because it thinks there are open sub-tasks on Done stories

Kurt Smith February 10, 2021

When we looked at the story all the sub-tasks showed Done or Cancelled.  Has anyone encountered this before?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 10, 2021

Are all the sub-tasks in the last column on the board?

Kurt Smith February 11, 2021

Yes, they were all in Done status and that status is mapped to the last column of our board

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 11, 2021

And cancelled?  Is that mapped into the last column too?

Also, could your board filter be excluding any sub-tasks?

Kurt Smith February 11, 2021

We do have canceled unmapped so perhaps that's the problem.  I will map it into Done and see if we have any ongoing issues.  Thanks for your help!