There is no tab for Scrum board in Jira Cloud to set Working days. Isn't it available in current version?
I've found https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/
but it is not relevant:
Also "Remaining days" of sprint on Scrum board are shown as 5, but actually there are 7 days left.
Hi @Alex ,
If you are not able to find the working days option because you are navigating in the wrong direction please follow the steps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Oday Rafeh ,
I think, you missed to see the attached screenshot. as per the attached screenshot that is a team managed projects and this feature is not available for the team managed projects.
Regards,
SB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Alex ,
Welcome to the Atlassian community!
You may have missed some steps or don't have permission from that scrum board to change the working days.
Please follow the below steps.
Click on your work from home page >> 3rd option Board >> select your board name >> from right side click on 3dot >> configure board >> 8th option working days option.
Kindly check If you have any problem, Please let me know.
Please accept the answer If it helps you😊.
Regards,
Sanjen Bariki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Alex ,
Thanks for your prompt.
As i can see you are using team managed project So In the team managed projects there is no option to configure the working days. Working days setup only for the company project.
Please find the below link which is created by the atlassian team for this feature.
Hope you got your answer.
Please accpet the answer If it helps you 😊.
Regards,
Sanjen Bariki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Sanjen Bariki thanks. Could you advise how to convert the project to "company" type? Or create a new one for example? Or it is somehow limited to Subscription plans?
If there is such specifics for this feature - what is the process of updating documentation to relevant version? I am talking about https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/ for example.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Alex ,
Yes you can migrate the team managed project to company managed project but please make sure to check before what you will lost after the migration. Please find the below documents for the migration process and limitations.
such specific features mean, as you mentioned documents only for company managed projects. You missed to see .
Hope you got your solution.
please accept the answer If it helps you .
Regards,
Sanjen Bariki