Roadmap does not show the revised start and due dates

Robert Brissett May 6, 2021

Whenever I change the start or due date for an epic the date changes do not persist after a page reload.  Is anyone else experiencing this problem?

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 6, 2021

Hi @Robert Brissett,

Only when editing the change directly in the issue and when I forget to press enter after I update the date. When the cursor is still in the date field (and the change is not committed yet) and I reload the page, my update is reflected in the roadmap.

Just to make sure we're talking about the same thing: I did this on the standard roadmap of both a team-managed and company-managed project. And tried to edit dates:

  • by dragging the timeline bar in the roadmap to a different due date
  • by editing start / due dates in the issue itself
Robert Brissett May 6, 2021

I am working with a Road map for a team-managed project.  

From Issue Editor

  1. I open the EPIC in the issue editor
  2. I change the due date 
  3. it saves
  4. I reload the page
  5. ERROR: the previous date is shown.
  6. End

From Roadmap

  1. I open the roadmap
  2. I drag and drop the epic on the timeline
  3. I reload the page
  4. ERROR: the epic is shown on the original date.
  5. End

Suggest an answer