Hi,

is there a way to remove closed issues from the 'unscheduled' ones in Greenhopper ? I have a lot of issues that are closed as won't fix or not reproducable or things like that so they don't have a fix version. I really don't want them to be visible in the 'unscheduled' section of the planning board anymore.

regards,

Wim

1 answer

1 accepted

1 vote
Answer accepted

There are 2 options to 'remove' resolved or closed issues from greenhopper..

1. Add a custom context

http://confluence.atlassian.com/x/dpL2Cw

2. Use the default filters, like the 'Hide Done Issues'

use the 'hide done issues' button

Another workaround would be adding a fix version to those issues. I normally use the 'affected version' for this

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

612 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you