Hello support team,

 

Please let me ask you a question about task status.

We have a problem that our sprint couldn't finish correctly in spite of Done status. However, if we changed Close status, the sprint could close.

Would it be possible to finish a sprint with Done status?

 

Best regards,

1 answer

1 accepted

1 vote
Answer accepted
Jack Brickey
Community Champion
January 28, 2021

Issues in the far right column define completed issue when the sprint is completed. Simply map the desired status(es) to that column.