Background:
I'm looking for some advice or suggestions as to the optimal approach for partially complete rollover stories and velocity calculation.
Scenario:
Let's say a developer picks up a 5 point story near the end of Sprint 1. At the end of the sprint, they estimate that they have completed 2 out of the 5 points. However, when the sprint is ended, the story (and all 5 of it's points) will be moved in to Sprint 2. Assuming this is the only story in Sprint 1 the velocity for this developer according to JIRA will be:
Issue:
This is causing the following problems
Solution:
Only by writing custom code. A validator could reject bad values and return an error message.
Is this JIRA Server or JIRA Cloud? Do you have a plugin like ScriptRunner or no?