Prevent a Sprint START when in backlog is Blocker Bug

Nika Nizharadze
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 7, 2021

Hello everyone,

I need to prevent a Sprint START when in backlog is Blocker Bug.

1 answer

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Champion
December 7, 2021

There is no means of doing this. You need to reply on a process managed by the scrum master/team during game sprint planning/kickoff.