Present sub-tasks time in the story window

yinon.eitan April 11, 2021

Hey,

Is it possible to see the subtask's time estimation when I open a Story in the backlog (and it presented on half of the screen, not open on its own tab)??

Thanks in advance,

Yinon Eitan

1 answer

0 votes
Prince Nyeche
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 11, 2021

Hi @yinon.eitan 

I believe the new issue view now has an "include subtasks" on the time estimate so it rolls upwards to the parent issue. Even if it's opened on the backlog view, it should render that rollup.

yinon.eitan April 12, 2021

Hey Prince, 

Thanks for the fast replay.

I will explain more clearly my question with a picture. 

This is what I see when I open a story that has sub-tasks. 

There is a way that I could see here each subtask time estimation? 

Capture.PNG

Prince Nyeche
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 12, 2021

No such feature is not available yet.

yinon.eitan April 12, 2021

OK thanks for the answer. 

 

In the old view, we could see it, and it's very helpful for us when planing a new sprint. 