Dears,
I have created a project as team managed project, however I have situation where I need to start two sprints parallel to meet deadlines.
Well I can achieve this by taking out sprint as feature but that will be just bunch or epics, stories in Kanban and manual groupings may needed.
I would like to know is there any way we can enable parallel sprints for team managed project... as a jira admin I have already enabled parallel sprints but this is not helping.
Thanks,
Kranthikumar Palle
Deliver Manager - NOEMA.
Hello @Kranthi kumar
Parallel Sprints is not available for Team Managed projects. Refer to: https://jira.atlassian.com/browse/JSWCLOUD-17195
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Look at this post
https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
\
Hey Vero.. this is for company -managed.. my question is specific to team -managed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.