Hello all,
could someone explain why I cannot see sum up of Original Estimate from Sub-tasks on parent Story in Scrum board backlog but I can see sum up of Remaining Estimate from Sub-tasks when board Estimation is configured for Estimation Statistic > Original Time Estimate and Time Tracking > Remaining Estimate and Time Spent?
So question is why I see Remaining Estimate from Sub-tasks? It doesn't make sense in case that I cannot see Original Estimate from Sub-tasks
Thanks in advance
Regards
Petr
Welcome to the Atlassian Community!
It's because sub-tasks are not sprint items. Any estimate on them is not a sprint estimate, so the report ignores the estimate.
Hello Nic,
I know about that. My question is why in that case I can see Remaining estimate from Sub-tasks in backlog summary. See my screenshot. It is summary of Remaining Estimate from Sub-tasks which belong to Stories. So I cannot see Original Estimate from Sub-tasks but can see Remaining Estimate from Sub-tasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.