Wojciech Dzięciołowski January 25, 2021

Hello! It's my first post here, so give me a feedback if I did something wrong :)

 

Problem description: In my organisation we log Original Estimate, Time Remaining and Time Spent in the subtasks, but only the last two fields are summing (inherit) into Story (parent). Ultimately, we would like to have all the working times in the Story.

Example:

Subtask (Child):
image.png

Story (Parent):
image.png

I am also surprised that in the old JIRA view, time tracking chart is displayed with correct values:
image.png

Is it a JIRA configuration problem?

3 answers

1 accepted

0 votes
Answer accepted
Wojciech Dzięciołowski May 4, 2021

Thank you for all comments. What I didn't realize was that the Original Etimate field in Story was completely unrelated to it's Subtask counterpart. Problem solved, Original estimate from Subtasks is summed and displayed on Time Tracking pop up.

0 votes
Daniel Ebers
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 31, 2021

There has been a longer discussion on it and, finally, the corresponding Suggestions has been implemented and currently is in with resolution "Fixed" - so it should work.
https://jira.atlassian.com/browse/JRACLOUD-70150

Referring to the last comment over there I am wondering if you can see the original estimate from the Story when you go to (...) >> "Log work"

grafik.png

In my case it looks like above (the screenshot shows the Story) whereas I solely logged:

  • 2d (Time Spent on Sub-Task) along with
  • 4d (Original Estimate on Sub-Task).
0 votes
Hessel F January 25, 2021

I assume that your stories will last longer than one sprint and is that the reason you'd like to carry over all the estimates?

Do you anticipate creating new subtasks for the stories that were carried over, or would you like to CLONE the story with the existing subtasks?

Our stories usually last more than one sprint. What we do is we clone stories but not subtasks.

Wojciech Dzięciołowski January 25, 2021

1. Yes, our stories sometimes last longer than one sprint, but I need all the estimates for analyses.

2. I've witten about new subtasks, and I usually create them by "Create Bulk  Sub Tasks" option.

Suggest an answer