As the project manager, I'm exploring ways to prevent others from changing the initial task estimates while still allowing the logging of hours. Any suggestions or solutions would be appreciated.
I think you can remove the time tracking field from the Edit screen and just leave it on the View screen and then you can add a transition screen with the Time Tracking field and set a condition for the transition and allow only users that you want to edit the original estimation.
The transition can point to the same status so it won't change.