Merging two backlogs to create a sprint

I have two projects which are to be implemented by one team. Have created backlogs for each project. For sprint planning I want for instance I active sprint to pull issues from both projects. Or initially create a backlog for both projects. I can not find a solution for that. That is why I had to create two active sprint sprints for the the two projects.  

 

Thanks

 

Ivo

2 answers

This widget could not be displayed.

Sprints and backlogs belong to boards, not projects.

All you need to do here is create a new Scrum board that has a board filter like "Project in (ABC, DEF)" so it looks at both projects.  So it can then attach a backlog and sprint to them in one go.

This widget could not be displayed.

there is another exotic solution.

you can work with backlogs separately and create two active sprints and than create a board where use filter like "project in (A, B) and sprint in openSprints ()

such approach will give you the opportunity to work with backlogs separately in case you have not the same person in a role of PO for example. SO it might have some benefit. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,478 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you