Hi,
Is there an ability to create a planning/roadmap, in the context of fix versions? I would like to define a dependency between versions, and then - when I push a specific version's date, the entire plan is being automatically pushed. Thanks!
Hi @orsu
That is an interesting idea... It appears that you have Basic Roadmaps rather than Advanced Roadmaps. Is that correct? If so...
With Basic Roadmaps I believe the dependencies are only driven by the Start Date and Due Date, rather than any other criteria. To do as you suggest driven by changes to versions, you could use automation rules triggered on Version change triggers, and then update the included Epics' dates.
Here is some information on the automation rules to get you started:
https://www.atlassian.com/software/jira/automation-template-library#/label/all/1453
Best regards,
Bill