Hi,
I have a task "A" and task "B" under an EPIC.
In Advanced roadmap plan task "B" has dependency on task "A"
If I change [Due Date] of task "A" by 2 days, I want the [Start Date] of Task B also to move by 2 days automatically.
Would appreciate any guidance.
Thanks
This post talks about using the Auto-schedule option to adjust the dates for tasks that have dependencies: