You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi,
I have a task "A" and task "B" under an EPIC.
In Advanced roadmap plan task "B" has dependency on task "A"
If I change [Due Date] of task "A" by 2 days, I want the [Start Date] of Task B also to move by 2 days automatically.
Would appreciate any guidance.
Thanks
This post talks about using the Auto-schedule option to adjust the dates for tasks that have dependencies: