Jira Advanced Roadmap change start date and end date of dependent issue

Munir Patel November 29, 2022

Hi,

I have a task "A" and task "B" under an EPIC. 

In Advanced roadmap plan task "B" has dependency on task "A"

If I change [Due Date] of task "A" by 2 days, I want the [Start Date] of Task B also to move by 2 days automatically.

Would appreciate any guidance.

Thanks

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 29, 2022

This post talks about using the Auto-schedule option to adjust the dates for tasks that have dependencies:

https://community.atlassian.com/t5/Jira-Software-questions/Simple-dependency-chain-auto-scheduling-in-Advanced-Roadmaps/qaq-p/1638895

Munir Patel November 30, 2022

Thanks Trudy for the link. It helped. 