Jira Advanced Roadmap change start date and end date of dependent issue

Munir Patel
Contributor
November 29, 2022

Hi,

I have a task "A" and task "B" under an EPIC. 

In Advanced roadmap plan task "B" has dependency on task "A"

If I change [Due Date] of task "A" by 2 days, I want the [Start Date] of Task B also to move by 2 days automatically.

Would appreciate any guidance.

Thanks

1 answer

0 votes
Trudy Claspill
Community Champion
November 29, 2022

This post talks about using the Auto-schedule option to adjust the dates for tasks that have dependencies:

https://community.atlassian.com/t5/Jira-Software-questions/Simple-dependency-chain-auto-scheduling-in-Advanced-Roadmaps/qaq-p/1638895

Munir Patel
Contributor
November 30, 2022

Thanks Trudy for the link. It helped. 