Hi,

When starting a Sprint, some issues go to the active sprint but the remaining stay at the original Sprint. This means we end up with both an active sprint ABC and sprint ABC and the issues split among the two.We then have to manually move the issues to the active sprint.

I checked both jira and greenhopper logs and found nothing suspicious.

This is GH 6.1.4.2

Has anyone experienced this by chance?

Thank you!

1 answer

1 accepted

Adolfo, can you provide exact steps to reproduce it? Perhaps a screenshot would help too.

Cheers

This is when I start the sprint:

This is what I get (note that 5 issues where not included in the active sprint):

Adolfo, this issue would be better handled by Atlassian Support, considering it needs further investigation.

Please raise a support ticket at https://support.atlassian.com to have an engineer's help.

I hope it helps.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,007 views 5 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot