Issue types for sub-tasks

Omril November 13, 2022

Hi everyone!

 

We want to be able to add sub-tasks to issues that will appear as bugs. We've opened a new sub-task issue type in the sub-task page, but we can't find anywhere to change the issue type - Not in the sub-task screen and not in the father issue (task) screen.

Anyone knows how to do that?

Thanks!

2 answers

1 accepted

2 votes
Answer accepted
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 13, 2022

Hi @Omril and welcome to the Community!

Creating a new sub-task issue type in Jira's global configuration will only work for Company managed projects.

To make it available in your projects, you will have to:

  • add it to the issue type scheme used in those projects;
  • decide what configuration the issue type will use in those projects, by also having a look at the workflow and screen schemes in your project(s).

This may take a bit of a learning curve, so be sure to have a look at the following support articles to learn more:

Hope this helps!

Omril November 15, 2022

Thank you very much! The problem was that I didn't associate the issue type to the project. I didn't understand it's needed on sub-tasks as well.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 13, 2022

Welcome to the Atlassian Community!

This may be down to the type of project you are using.  Have a look to the bottom of the column on the left of your page - it'll tell you whether the project is team or company managed.

If you are in a team-managed project, it's simple - these do not support different types of sub-task (yet), it's either sub-tasks or no sub-tasks.

In a company-managed project, you can have as many sub-task types as you would like, and @Walter Buggenhout has given you the rest of what I would say about configuring and working with them.  But I think you asked about changing the sub-task's type as well - in a CMP, you can use the "move" option to change the type, or, if you put the issue-type on screen, you can directly edit it to be another one, if the two types are using the same configuration.

Omril November 15, 2022

Thanks! It is a company managed project, and with the rest @Walter Buggenhout _ACA IT_ did help me.

Suggest an answer