Hi All, 

It seems that even a secretin status (Rejected)is set with 'Done' StatusCategory (Green color) on the workflow. when I complete a sprint I still see the items as 'UnDone' and I am required to move the items back to the Backlog \ move to next sprint.

Any directions \ workarounds so I can fix it Reject.JPGbl.JPG

Anyone can assist ?

 

2 answers

1 vote
KAGITHALA BABU ANVESH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 4, 2021

Hi @David Peles ,

Please go to board 

1. let's check does the "Reject" status is placed under "Done" column.

2. any resolution is chosen while "Reject" jira Task.

 

If above both are placed correctly , then there is no issue.

  

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 4, 2021

Hi David,

Make sure the Reject Status is in the last column. Only statuses in the last column on a Sprint board will be considered "Done" and not moved. 