Is there a way to edit the end date once a sprint has started?

Accidentally started a sprint (on the Rapid Board) and it's been running a while before we realised that it's end data was July, not June. (Hadn't noticed the date picker had moved forward a month).

Is there a way to change this date with the sprint running so that all the burndown charts etc show proper graphs? I cannot find an option for this.

2 answers

1 accepted

Sure. In plan mode expand the Sprint summary box at the top of the backlog then click the dates to edit them.

Thanks,
Shaun

Thanks, that was it. I was certain I'd looked there. Guess I was wrong.

Thanks, that did it. I was certain I'd looked there.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

12,407 views 15 13
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you