Is there a way to populate fields of a task or story that is linked to an EPIC with the field designated in the EPIC?
such as FIX VERSION, PRIORITY etc
Hi Eleanor,
Yes you can copy the values of fields in an Epic down to linked Tasks by using Automation for Jira.
However, what type of project is it - Team-managed (Next-gen)? Or Company-managed (Classic Software)?
The project is Company-managed (classic software)
Thank you - will check the solution ( Automation for Jira).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have found the solution thank you!
added automation -
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi eleanor
We have the same requirement.
In edit issue fields section what did you do exactly?
Can you show the details?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
👋 Hi there Jira Community! A few months ago we shared with you plans around renaming epics in your company-managed projects. As part of these changes, we highlighted upcoming changes to epics on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.