In Advanced Roadmap (Plan) you can specify Estimates in days. How can you configure holidays?

Nayantara Patel
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 3, 2021

I'd like to use Estimates in days for a JIRA Plan (Advanced Roadmap).   However there are some company holidays coming up and I'd like the projected date to account for those holidays.   Is there any way to configure holidays?  Will the projected day for an issue to be completed, only use week days and not weekends?

1 answer

0 votes
Robert Wen_Cprime_
Community Champion
October 4, 2021

So, you should add the holidays as non-working days in JIra.  Here's the documentation page: https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/

Rory Standley March 15, 2022

Does this have any bearing on Advanced Roadmap?