Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

I can't seem to move my timeline bar

I tried to utilize the timeline bar in a project but I cannot move it:

timelinebar.jpg

All of my timeline bars are part of an Epic, and all of them are added in sprints. What I want to do is for our sprints, I should be able to adjust the bar to reflect the dates (For example, development takes place on the first 8 days, then testing is on the 9th and 10th day, etc.)

How do I achieve this?

2 answers

0 votes
Becky Brooks - Visor for Jira
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Oct 19, 2023

Hi @David Christopher Castillo ,

Correct me if I'm wrong, but it looks like your bars are part of an Epic with their own sprint dates (not an Epic themselves.) if so, then know Timeline bars "are supported for only Epics." 

More explanation provided here from this ticket (when Timeline was called Basic Roadmaps) : https://community.atlassian.com/t5/Jira-Software-questions/How-to-show-the-timing-bar-in-roadmap-mode-for-all-issue-types/qaq-p/1825076

"The roadmap (now Timeline) view is designed for the epics and it's progress over a period of time. This is because, as per Scrum framework the product owner (business stakeholders) plans for a release date/ period given the market demand.

As we know the epics has user stories spanned either within a single project team or across project teams. So, epic time line view will be an apt and primary functionality."

 Solutions available to you:

1. You'd need to upgrade to Premium for Advanced Roadmaps to have more control over what bars are adjustable.

2. You can also use a 3rd party tool to create Gantts/ Roadmaps, like Visor:  https://marketplace.atlassian.com/apps/1226209/visor-flexible-spreadsheet-for-jira-roadmapping-bulk-edits?hosting=cloud&tab=overview

 

I hope that helps. 

0 votes
Rachit Singhal
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Oct 19, 2023

Hi @David Christopher Castillo ,

 

You can do the scheduling of your Jira issues - start date and due date which will be shown here.

 

For your requirement of development in 8 days, testing is on 9th & 10th? Can you please elaborate are you maintaining this data in any field?