The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to transition parent task when at least one sub-task is in a given status

serge calderara
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 11, 2022

Dear all,

I have a use case where I am not finding the propay way to handle it.

I have a parent issue which is has also different sub-tasks.

What I need to do is that when at least one single sub-task is in status In Progress, I need to transition the parent issue to In progress.

Any idea how to accomplish this using project automation ?

regards

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

serge calderara
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 17, 2022

Yes I have seen it but is using scripting.

I manage to make it work using project automation

Tuncay Senturk _Snapbytes_
Community Champion
January 17, 2022

Ah, I see, I'm sorry I didn't realize you wanted to make it work with Automation.