How to transition parent task when at least one sub-task is in a given status

serge calderara
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 11, 2022

Dear all,

I have a use case where I am not finding the propay way to handle it.

I have a parent issue which is has also different sub-tasks.

What I need to do is that when at least one single sub-task is in status In Progress, I need to transition the parent issue to In progress.

Any idea how to accomplish this using project automation ?

regards

1 answer

0 votes
Tuncay Senturk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 17, 2022
serge calderara
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 17, 2022

Yes I have seen it but is using scripting.

I manage to make it work using project automation

Tuncay Senturk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 17, 2022

Ah, I see, I'm sorry I didn't realize you wanted to make it work with Automation.

Suggest an answer