How to move defect to completed state during sprint completion

Vikram Singh Chouhan November 27, 2021

Hello,

I am new to JIRA. Currently i have a milestone and want to mark completed. All the stories and defects in it are marked as DONE (custom flow). when i trigger completee sprint it always show open issues. How can i make it work?

1 answer

1 accepted

4 votes
Answer accepted
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 27, 2021

Make sure the last column of your board has the done status issues. Also be sure to set the Resolution field when moving to Done.

Vikram Singh Chouhan November 28, 2021

@Jack Brickey : Thanks for sharing your thoughts. As you said, after moving issues to last column in the board, it started reflecting. Thanks a lot.

Suggest an answer