The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to get epics included in the product backlog?

Gustavo Narea
Contributor
May 16, 2013

We're currently running JIRA 5.2.4 and GreenHopper 6.2.1, and I cannot find a way to get epics listed in the product backlog. They do show up in the "epics" panel, but I need a way to include them in the prioritization of the rest of the backlog... Which you should be able to do in a product backlog.

I think it's not a problem with the Scrum board's filter, because I've tried this with a test board whose filter simply is "project = MyProject", and the problem is still present. I suspect that GreenHopper itself is excluding epics. Is this correct?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Christian Czaia [Decadis AG]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 16, 2013

As far as I know issues of type "Epic" are not in included by design

Gustavo Narea
Contributor
May 16, 2013

Thanks, Christian!

I was hoping that wouldn't be the case. It's just wrong: GreenHopper is mixing the concepts of epics and themes. You should be able to prioritize an epic along with all the other product backlog items. GreenHopper's "epic" panel actually works as a theme filtering device.

I raised this ticket: https://jira.atlassian.com/browse/GHS-8851