How do you create two levels under Story

Alison Whittaker August 25, 2020

I'm trying to create a structure of epic > story > task > subtasks but Jira is only letting me create epic > story > subtask. How do I get another level down, under story > subtask?

 

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 25, 2020

You do not.  The hierarchy in Jira Software is Epic -> Story -> Sub-task.  You can't add more layers without apps that add them.

Alison Whittaker August 25, 2020

Thank you! One more question... Can you create a layer above epic then?  Initiative>epic>story>subtask?

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 25, 2020

Advanced Roadmaps, Jira Align, and Structure all have options for layers over Epics