Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I create a query for a status change within a sprint

Jim Henry
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 14, 2017

I need to create a query that will show the date a status was changed to a specific status within a sprint.

I was able to create a query for the status change within date frame but this will not work since I need to talk about the report throughout the sprint.

Is there anyone that can help me.

 

1 answer

1 vote
Josh Steckler
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 14, 2017

A query isn't going to show a date. If you need to show a date that a specific status was entered, you should create a date custom field and set that date with a workflow postfunction when the inbound transitions to that status are executed.

Suggest an answer

Log in or Sign up to answer