How can I modify the date an issue was added to a sprint?

We had to re-create our JIRA Agile project in the middle of the first sprint. Our sprint started on Oct 28, but we re-created the project on Nov 06. Everything worked fine except that the burndown chart shows all issues added to the sprint on Nov 06 which makes the chart look wrong.

Is there a way I can modify the date JIRA Agile thinks the issues were added to the sprint to fix our burndown chart?

1 answer

Hi David,

For that, it would be necessary to perform database changes, which unfortunately is not allowed on JIRA Agile Cloud.

Cheers,

Clarissa.

OK, well thanks for the info.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

845 views 5 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot