How can I hide sub-tasks within a sprint's work view?

I'd like to hide sub-tasks from each sprint's Work view and instead just have parent issues transition through columns. Is this possible / how can I do this?

If it's helpful/relevant I'm using JIRA Agile.

2 answers

You may have given the source data as your project for the agile board.

Instead of specifying the project , let the agile board take data from a filter. This filter will strip out the sub-tasks.

say,

project=<my_project> and issue type NOT IN (sub-task)

If this is given as input you should NOT see sub-tasks in the work mode.

Rahul

1 vote
Steven Behnke Community Champion Feb 24, 2015

In addition to @Rahul Aich [Nagra]'s post, you may ALSO apply a quickfilter to temporarily hide sub-tasks on a board. Configuring Quick Filters

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,221 views 6 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot