We use Epic and Version filtering in the backlog view. How can I add a column like epics but for initiatives?
Hi @Mark Collins,
You can't, unfortunately.
If you do have initiatives, I guess you are on the premium plan. So use your advanced roadmap plans to plan from the higher levels of the hierarchy instead.
Also, here are some of the suggestions to add filter options for initiatives, which you may review and vote for:
Best regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank you @Walter Buggenhout
We were on the advanced plan but have dropped to basic. Thus we have initiatives to aggregate epics under an umbrella but no useful way to utilize them well.
The linked suggestions from @Bill Sheboy address this gap.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.