Hello,
I have added a new status in the workflow, but now, in the burn down chart the issues in status DONE are not displayed in DONE section, and it's like no issues were finished during the sprint!
This is the new workflow:
Burn down chart:
We have DONE issues (green), but are not counted as DONE:
Burn down happens when issues are done according to the board, not the status directly.
The board's definition of "done" is simply "the last column on the board".
So, indirectly, the status does determine it - the column definitions are "issues in one of these status".
My guess is that your "done" status is not in the last column on the board.
Thanks for your comment Nic!
I did not add any column in the board, I just added a new status to be used in the issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That's fine, but it probably hasn't got anything to do with your burn-down going missing. Unless
Could you take another look at the status mapped into the very last column on the board?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Robert,
But I don't see in jira what I need to change.
And I don't understand, because DONE issues where displayed properly in burn down chart, and the only thing I've done is adding a new status (type To do), and now I have this problem...
More information please?
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For the four issues in the DONE status, was the resolution set? Jira doesn't consider them closed unless the resolution is set.