For approvals in Jira Work Management project; Approve a transition when x number of people approve

Olliver Ordell April 18, 2024

In a Team-managed Work Management Project, you can set up Approvals for a given status. I currently have an approval step, with 3 people as "Preset approvers". As of now, the issue won't transition before all 3 people have approved the issue.

I am looking for a way to specify that e.g. 1 or 2 out of 3 approvers is enough to trigger the transition. Is that possible somehow?

1 answer

0 votes
Krzysztof Bogdan April 19, 2024

Hi @Olliver Ordell 

You could use Approval Path for Jira. There is a group set where you can define how many approves are required.


Best,

Krzysztof Bogdan