Hello,
I want to show on the issue preview the original estimated time and not the story points field. How can I change this preview?
Hello @Maria
Welcome to the Atlassian community.
Are you working with a Team Managed project or a Company Managed project?
Are you working with a Scrum board or a Kanban board?
Hello Trudy.
Thank you for your answer.
It's a Company Managed project using a Scrum board.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Maria,
The information that is displayed is based on what you have set for the Estimation Statistic for the board. You would need to change that to Original Estimate to show the Original Estimate value on the cards. That option is under Board Settings > Estimation.
Note that will also change the lozenges that appear in your Backlog on the cards and summary for the sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.