Field on issue preview

Maria April 17, 2023

Hello,

I want to show on the issue preview the original estimated time and not the story points field. How can I change this preview?

 

Captura de pantalla 2023-04-17 a les 17.13.56.png

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 17, 2023

Hello @Maria 

Welcome to the Atlassian community.

Are you working with a Team Managed project or a Company Managed project?

Are you working with a Scrum board or a Kanban board?

Maria April 18, 2023

Hello Trudy. 

 

Thank you for your answer. 

 

It's a Company Managed project using a Scrum board.

 

Thank you

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 18, 2023

Hello Maria,

The information that is displayed is based on what you have set for the Estimation Statistic for the board. You would need to change that to Original Estimate to show the Original Estimate value on the cards. That option is under Board Settings > Estimation.

Screen Shot 2023-04-18 at 9.43.08 AM.png

 

Note that will also change the lozenges that appear in your Backlog on the cards and summary for the sprints.

Screen Shot 2023-04-18 at 9.45.18 AM.png