I want to set up the estimated time of a task. But, if I establish the estimate time in the sprint board, I don't see this estimated value on the task detail.
I tried set up in the screens configuration, in the issues configuration and I don't see this parameter to assign it.
Also, I created a custom field, I assigned to the screen but it doesn't work also.
So, I want to know how can I set up the estimated time of a taks with the objective of register a value on that field and have the analysis between the estimated, remain and logged time.
Make sure you add the Time Tracking fields to your screens. Those fields are built-in from JIRA, no needs for custom field.
If you manually edit your issue, can you edit the Estimates?
Yes I can, but I don't know how to set the Estimated Time, as you can see in the last image, there is as "Not specified".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Would you happen to be at the summit right now? I could debug this with you if you have the time.
It seems to me that it's a misconception or misconfiguration, the steps are pretty straightforward:
- Add Time Tracking to the screens (make sure its the official time tracking, not a custom created one)
- Make sure you board as the Estimation configured properly (go in Configure Board)
That's it ... you should get your estimates.