Hi Team,
We have a need to use the same Epic across 2 different teams' projects...
Both teams will have separate User Stories tied to that Epic, however they may be scheduled across different Sprints.
Now, if we do use the same single Epic for those 2 projects, will it have ANY impact on Sprint completion/velocity report?
For example, will Team A not be able to Complete Sprint 1, because Team B has a user story tied to the same Epic but scheduled for Sprint 2?
And if it is possible, will this have any negative impact on Team A velocity report?
Thank you!
Agata
Epics are not part of the Sprint, their Stories are : this will not have any impact on the sprint velocity or your ability to close a Sprint.
Velocity report is also based on the Story points that are specified for your stories (Epics should not have Story points estimates), so no impact there.
Let me know if this helps,
--Alexis
Calling all Confluence Cloud Admins! We created a new Community Group to support your unique needs as Confluence admins. This is a group where you can ask questions, access resou...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.