Documentation for Evidence Based Scheduling according to GHS-1656

According to the Issue GHS-1656 "Evidence Based Scheduling" is implemented in versino 4.1 and I would like to understand how to use it.

What I need is some way to predict the unscheduled items release date, e.g. which SPRINT they will be done according to the current Velocity estimate.

Today I use "Statistics" and set the Capacity to, for example, 20 Story Points. Then Greenopper shows, by adding a horizontal line with information about the Story Points, which use cases wil be possible to include in the first SPRINT. I would like to have indications for several SPRINTs. Just adding yet some more horizontal lines would help. Can I do that?

Regards

Anders

1 answer

1 accepted

I solved my problem by counting the number of SPRINTs left until the release and multiply it with our predicted velocity. Then I added that as our Capacity and got an estimate of what will be possible to include in the Release. Maybe not exactly what I wanted but good enough for my purpose.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,229 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you