Complete a sprint - All tickets from the sprint are considered as open

Caroline SIOUFI January 4, 2022

Hello,

When I try to complete my sprint, all the story are considered as open which is not the case.

So it proposed to move the story to an other sprint.

All of them have a done status. 

JIRA1.PNGJIRA2.PNG

I though maybe it was because of the open status of the epic linked but even if it is done as well the result is the same.

Do you have any idea on what is the problem here?

Thank you in advance.
Regards,

Caroline

1 answer

1 vote
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 4, 2022

Hi Caroline - Welcome to the Atlassian Community!

The Done status needs to be in the far right column of the board for the issues to be considered complete. Issues are only complete that are in the very last column of the board. 

Suggest an answer

Log in or Sign up to answer