Hi guys,
we have two projects with two different boards and different sprints and tickets. I know the issue, that when you move a ticket from project A two project B, that already was in a sprint in Project A, the Sprint is also moved to Project B.
That issue happened now and unfortunately this sprint was started in Project A and is now also active in Project B.
Is there any chance to delete / close / remove this active sprint in project B without closing it also in Project A?
When I try it I get the error, that there are still open tickets in this sprint.
Thank you for your replies.
Cheers, Lars
Hello @Lars Blaschka
The sprint will show in any agile board where there is an issue that fits that boards criteria that also has been assigned to the sprint. Sprints will also show up in the board in which they were created, regardless of the issues assigned to the sprint.
The Sprint from project A has not "moved" to the agile board for project B. Rather it is just visible there also.
To fix that, you must find all the issues in the Sprint that fit the criteria for the project B agile board, and remove those issues from the sprint.
Catch up with Atlassian Product Managers in our 2020 Demo Den round-up! From Advanced Roadmaps to Code in Jira to Next-Gen Workflows, check out the videos below to help up-level your work in the new ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.