I want to see the timeline for the main epic as well as the smaller breakdown of timelines with the due date for each task. Right now I only see the timeline for the Epic and not the individual tasks. Any advice?
For me it was well hidden, but i finally found the trick:
https://community.atlassian.com/t5/Jira-Software-questions/Child-issue-start-and-due-dates-on-Road-map-Roadmap-for-several/qaq-p/2251148#U2478665
Yes in the year since this question was originally posted, new features have been released and the timeline for child task can now be added to the Basic Roadmap (aka Timeline) display for Software projects in the Free and Standard plans.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
With the Standard Jira Cloud subscription you have only the Basic Roadmaps functionality. That allows you to see only the timeline for Epics.
You would need to upgrade to the Premium Jira Cloud subscription to get the Advanced Roadmaps functionality to see the timeline for child tasks. Or consider a third party app for your roadmap features.