Can I change the displayed order of sprints under a release?

Somehow one of may users has created a release and associated sprints which show like this in the planning board view

Release 1.00

|_Sprint 3

|_Sprint 2

|_Sprint 1

Is there a way of re-ordering the sprint or are we stuck with this order (which I assume is the creation order)

Cheers

Norman

1 answer

1 accepted

0 votes
Answer accepted

I suspect that it's down to the order of the versions and how they were created. You should be able to re-order them in the Manage Versions screen

http://confluence.atlassian.com/display/JIRA/Managing+Versions

Doh! why didn't I think of that :-)

Cheers

Norman

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

593 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you