Our client would like to see two separate curves in the Hour Burndown Chart. One for standard Issue types and the other for their sub-tasks. Is this possible? How can this be set up?
You can do it via Contexts in GreenHopper which you can use to produce different graphs with different sets of data
1. Go to your chart board
2. Select the project then select the drop down to the right of the project name, it will probably say Default of On-the-fly.
3. Select New & you will get a popup for a new context which can be based on an existing filter (subtasks JQL: issuetype in subTaskIssueTypes()) or by selecting different fields to filter by. (standard issuetypes JQL: issuetype in standardIssueTypes())
4. Create a context based on sub-tasks only and one based on standardIssueTypes.
5. Look at your lovely charts based on two different sets of data.
BTW Are you rolling up your time from sub-tasks to the main task?
Hello Matthew,
thank you for your answer.
No they aren't rolling the time from sub-tasks to the main task. The work is logged on each sub-task separately and is not present in the main task.
This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.
Read moreCan a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...
Connect with like-minded Atlassian users at free events near you!
Find a groupConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no AUG chapters near you at the moment.
Start an AUGYou're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.