We have a large project (~400 issues) with an estimated end date and we work in sprints. I would like to be able to show a burndown chart for the total project to track our progress. I know a burndown by project is not available in Jira. I thought about creating a second sprint, but issues would cross both sprints, so that won't work. Does anyone have a workaround or app that could accomplish this? I've looked at a simple chart in Excel, but that's mostly manual.
Hi @Mary Stahly
You can create consolidated burn down either using Excel (which is mostly manual as you mentioned) or you can try using eazyBI. Take a look at this page for a wonderful explanation.
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.