Hello, based on this setup:
What would be the recommended method to hide CustomFieldA and CustomFieldB on the Task create screen for Project1 through Project9, but show them for Project10?
Community moderators have prevented the ability to post new answers.
You could include CustomFieldA and CustomFieldB in the create screen for all projects, but in the Field context for CustomFieldA and CustomFieldB, limit the context to just being available for Project10.