The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Automation for Custom Field to Start Date and Due Date for Advance Roadmaps

Ana Murphy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 19, 2023

Hello, I'm seeking assistance on how to configure an automation that can automatically fill in the start date and due date from a custom field. This way, these dates can be showcased in the advanced roadmap.

Assets Due Date should be linked to the Start Date,

Article Live should be linked to the Due Date.

help.PNG

 

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Mikael Sandberg
Community Champion
October 19, 2023

Hi Ana,

This should be fairly simple to do with automation and smart values. If the custom field is of the date type then all you need to do in your automation is to assign the value of that custom field to the start date/due date like this:

Screenshot 2023-10-19 at 3.25.06 PM.png

You can learn more about smart values here.