Hi, I have a common proect managment problem to solve but I can't find the way.
I need an automation that aligns due date between linked tasks (subtasks with parent or linked iessues with blocks connections).
...Any advice? There's aready this kind of automation available?
Hi @Degio and welcome to the community!
You could do something like this:
Hi Mark. Thanks so much.
I just tried your solution and is perfectly working ;)
Thanks and best regards.
Degio