Assign subset of sub-tasks for a User Story to a sprint.

Is it possible to assign the sub-tasks for a particular user story to different sprints? For example, we have a project that has a User Story comprised of several sub-tasks that all together will take about 5 weeks. Their sprints are 2 weeks long. They don't want to break the story into two separate stories, but instead want to have some of the sub-tasks in one sprint, and the rest in another. Currently, they're having to let the ones they didn't get done fall into the backlog at the end of a sprint, but that's not ideal as it skews their stats. Is there a way to organize sub-tasks in the sprints separately from their parents?

Any help or clarification would be appreciated.

Thanks!

1 answer

1 accepted

This widget could not be displayed.

Hi Kim,

Unfortunately, there is no way to do that except breaking the story in two or three small stories. All the sub-tasks need to be on the same sprint as the parent issue. If you have issues that take longer than a sprint, you probably can break the stories into small ones or your sprints need to be longer.

Hope it helps!

Cheers,

Clarissa Gautério

Atlassian Support

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,434 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you