Am I able to have sub-tasks be created having the same status as their parent?

I would like to be able to create sub-tasks that have the same status as their parent.

When creating a sub-task on a task board it would be useful as the sub-tasks would appear nested immediately under the parent issue. From here they can be moved independently.

Is there any way to setup the a workflow to do this?

1 answer

It is not possible have subtasks to have the same status of Parent on creation. The initial status is always the one you configure when creating the workflow and this cannot change dynamically.

Is this really true? Seems I have this working in my development environment (don't know how), but it's not working in my prod environment (don't know why). We're using version 6.4.8.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

13,255 views 15 14
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you