I created advanced roadmap /plan from two projects.
I wanted to see Intiative status - an Initiative that has three Child Epics, however in the advanced roadmap, these epics are showing up as epics without parent.
As you can see from the picture below, these epics have Initiative 112 as Parent.
Picture1- Advanced Roadmap Epics showing up as as epics without parent
Picture-2 Epic details show that Initiative-112 is parent (however I don't see a parent link in Epic details)
Hi @Prashantha
You have to add the field "Parent link" to the Epic and update it with the initiative ticket.
More details in https://support.atlassian.com/jira-software-cloud/docs/link-issue-to-a-parent-in-advanced-roadmaps/